Alberta scaffold rules.

What does Alberta Part 23 require of a scaffold?

Part 23 of the Alberta Occupational Health and Safety Code covers scaffolds and temporary work platforms.

Checked on 2026-11-04

The standard the Code cites

Section 323 names the standard for a scaffold used to build, alter, repair, or demolish.

Edition The current CSA edition is S269.2-16 (R2026). The Code text still cites the 1987 edition.

Pole scaffold ties

Section 324 sets the tie spacing, and only for two kinds of scaffold.

Winter enclosures and hoarded ties

Section 324
Section Plain words
s.324(1)(b) Unhoarded. 4.6 m vertical and 6.4 m horizontal.
s.324(1)(c) Hoarded. 3 m vertical and 3 m horizontal.
s.324(4) Hoarded masonry walk-through frames. One tie for each 9 m². Vertical tie-ins 2 to 3 m apart.

Not this table System and frame scaffolds follow section 331, not this spacing.

The load

Four times the load

Section 325 sets the strength of the scaffold, and the load a crew may place on it.

A tube-and-clamp scaffold bay with a wood deck on the ledgers and a diagonal brace into the couplers.
Section 325
Section Plain words
s.325(1) Designed and built to support at least four times the load that may be imposed.
s.325(2) The load on the scaffold never exceeds one quarter of the design load.
s.325(5) Workers are told the maximum load.

King's Printer, Part 23

A tag at each entry

Section 326 is the public rule for colour coded tags.

Scaffold tags in Alberta, the full guide

  • Green Safe for use.
  • Yellow A potential or unusual hazard.
  • Red Unsafe for use.

Rolling scaffolds

Section 334 sets two limits. Both are multiples of the base, not a fixed height.

Rolling or fixed scaffold?

Elevating platforms

Section 347 does not send an elevating platform through the tie table.

Ladders, planks, and platforms (ss.327 to 330): see the measurements guide.

Ladders, planks, and platforms — the measurements

Not a rolling scaffold A rolling scaffold stays with the ratios in section 334.

Questions.

Which standard does section 323 cite?

CAN/CSA S269.2-M87 (R2003), for scaffolds used in construction, alteration, repair, or demolition. The current CSA edition is S269.2-16 (R2026). The Code text still cites the older edition.

Which scaffolds use the 4.6 m tie spacing?

Single-pole and double-pole scaffolds only. Unhoarded ties are 4.6 m vertical and 6.4 m horizontal. Hoarded ties on those scaffolds are 3 m and 3 m.

What spacing applies to hoarded masonry walk-through frames?

Section 324(4) uses one tie for each 9 m² of hoarding. Vertical tie-ins sit 2 to 3 m apart. That rule is not the pole-scaffold spacing.

How strong must the scaffold be?

Section 325(1) requires at least four times the load that may be imposed. Section 325(2) keeps the load to one quarter of the design load. Section 325(5) says workers are told the maximum load.

What do the tag colours mean?

Section 326 places a colour coded tag at each point of entry. Green means safe for use. Yellow means a potential or unusual hazard. Red means unsafe for use.

How tall may a rolling scaffold be?

Section 334 keeps the height at most three times the base. A worker rides it only when the height is at most twice the base. An elevating platform follows section 347, not this ratio.

Sources

Checked on 2026-11-04

Quoted from the Alberta King's Printer text of the Occupational Health and Safety Code.